POC (APS) | CT X DTS

APS Input Baseline & Scenario Estimates

The verified figures below come from the Siemens Opcenter APS import/export datasets (orders, routings, resources, BOM, supply). Everything derived from the 300 units/day operational assumption is a POC estimate, clearly labelled.

APS Input
POC Scenario Estimate — Not an official APS schedule

Unit records

2,673rows

Unit-level order records

APS Input

Management orders

9grouped

Grouped by base order ID

APS Input

Routing rows

266133 PL + 133 OL
APS Input

APS resources registered

133resources

All routing resource references resolve

APS Input

Operation time

98.4s per operation

Source UOM: S; header discrepancy noted

APS Input

Scenario output

300units/day

Baseline reference 300 units/day

POC Scenario Estimate — Not an official APS schedule
Order mix and quantity
Units per management order after grouping the 2,673 unit records. Total 2,673 units.
Output and duration sensitivity
POC estimate: how the 300 units/day reference and operation duration scale with a capacity change.
Routing coverage
266 routing rows split evenly between PL and OL products. No model names exist in the extract, so none are shown.
BOM & supply reconciliation
This is a reconciliation / data-quality view, not a stock or shortage statement. Inventory figures come from the supplied inventory workbook, not from APS.
MeasureValueProvenance
BOM requirements208
APS Input
Distinct BOM-required parts143
APS Input
Supply rows399
APS Input
Unique supplied parts311
APS Input
BOM parts with no supply record32
APS Input
Confirmed inventory match111
APS Input
No supply record found32
APS Input
Unresolved match0
APS Input
32 BOM-required parts are labelled “No supply record found” — this is not confirmed zero stock or a confirmed shortage. Supply may represent wider plant inventory beyond the PL/OL BOM extract, so unmatched supply rows are expected.
Delivery and scheduling status
The solved APS baseline is available, window 01 Jul 2026 00:00 04 Jul 2026 04:21 across 355,509 operation rows.
POC Scenario Estimate — requires APS reschedule for official result. Resource utilisation, queue time and per-order delivery buffer are not published in this static extract.
Imported due-date distribution
Units per imported due date. These are import due dates, not scheduled completion.
Product family split
Only PL and OL exist in the source. Orders and units grouped by the imported part number.
ProductOrdersUnitsProvenance
PL61523
Derived from APS Input
OL31150
Derived from APS Input
Data provenance
Every KPI, table and chart in this POC carries one of these states. Nothing outside the attached source files is presented as APS data.
APS Input

Read directly from one of the attached verified APS import/export files.

Derived from APS Input

Produced by grouping, counting or a simple transformation of the attached APS input files.

User-entered Assumption

Supplied or confirmed by the user; not present in any attached file. Editable in the Scenario Builder.

POC Scenario Estimate — Not an official APS schedule

Deterministic POC arithmetic from APS inputs and user assumptions. Not an APS result.

Not available from static APS input

Not present in the static import/export datasets; requires the APS SQL backup or on-premise backend.