Scenario Builder
Every input here is a user-entered or user-confirmed assumption, not APS data. Results are POC estimates.
133 resources are registered from the APS extract. All 133 resources are listed from ResourceGroup(1).csv; load, capacity, queue and utilisation are not available from static aps input.
Estimate: 300 units/day, duration factor 1, operation time 98.4 s, schedule window 76.36 h (+0.00 h).
+10% represents an upgrade, parallel equipment or a process improvement; −10% represents degradation or planned maintenance. Duration scales by 1 ÷ (1 + pct) on a 24/7 100%-efficiency calendar — it never means a longer day.
Factory assumption: 24/7 operation at 100% efficiency. A +10% capacity change therefore means +10% effective throughput — it does not mean a 26.4-hour day.
Downtime mode
Take a resource or the whole line down for a fixed number of hours.
Apply material scenario
Availability and demand percentages below take effect.
Ignore shortages
Mirrors the APS IgnoreShortages flag — shortages report as zero.
Include urgent order
Adds the quantity below to the sequence.
Displace existing orders
Insert ahead of the sequence.
BOM explosion estimate: 49,000 material rows (98 per unit) and 66,500 routing operations (133 per unit).
| Hierarchy node | Relationship | Required operators | Available operators |
|---|---|---|---|
| Main Line | Resources whose imported name contains "Mainline". | ||
| Sub-Assembly | Within Main Line — imported names containing "Sub Assy". | ||
| Feed Lines | Remaining station resources feeding Main Line. |